The team of our electricians that was hired to change two times 1,6 km cables on two ferries in the Baltic Area have finalized the job within time and budget.
The job for the second ferry changed due to time issues beyond our control and we were asked to increase the team from 10 electricians to 18 within two days.
We managed to do that to our clients satisfaction. Our client have expressed that they were very satisfied with performance and will be looking in our direction for future Cooperation.